Current Road Projects

Kellogg/US-54 Expansion 

Click HERE for a map of the improvements to be constructed. 

Freeway improvements announcements for the IKE Highway improvement Program are to be made by the end of January. East Kellogg Phase 2 Improvements through Andover were a high priority at the Local Consults meetings in preparation for the project selections.  

159th St Improvements Project 008 N-0692-01 US-54/400 to Central Ave

Project 008 N-0692-01 includes the construction of a three-lane curb and gutter section concrete roadway with underground storm sewers and concrete sidewalks on 159th St. East from Willowbrook St to Central Ave.

Work began on Phase 1 of the project on January 9, 2023 with the closing of northbound traffic between Willowbrook St. and Central Ave. for tree removal, grading, and construction of a new waterline, storm sewers, and concrete pavement on the west side of the project. Some public utility relocation work is also ongoing.

On Phase 2 (East side) of the project the contractor is wrapping up the paving of the roadway, sidewalk, grading. They will be installing pavement markings, signs and seeding the project and are on schedule to have the roadway open to traffic by the end of March 2024.

During construction communications may be directed to Project Superintendent David Nelson dnelson@pearsonconstructionllc.com with Pearson Construction or Project Inspector Jeff Curtis jacurtis@transystems.com with Transystems.

To view concept, please click HERE.

Founder's Parkway 

Founder's Pkwy from Yorktown Pkwy to Sunflower Ln is substantially complete. The Onewood to Allen St. Project is in progress for completion  in 2024. Preliminary engineering for the Allen St. to Andover Rd. and Andover Rd to Sunflower Ln. segments are underway for right of way acquisitions and construction in 2024-26. A $1.5m grant from the KDOT Access Management Construction Program was awarded to the Allen St. to Andover Rd. Project and a similar grant is pending for the Andover Rd. to Sunflower Project.   

Yorktown Parkway  

Preliminary engineering is underway for the Yorktown Pkwy BASE Grant Project from Central Ave. to 13th St. 

Please sure to follow the City of Andover on Facebook for frequent updates.